Total products delivery time (Order/Production/Delivery)

  1. by Sea 87-112 days
  2. by Railway + Sea 80-95 days
  3. by Air 62-70 days

Respective Products Delivery time (Order/Production/Delivery)

  1. Order procedures (confirmation, drawings preparation) 5 days
  2. Production time 40-45 days
  3. Arrangements/Loading 5 days
  4. Shipping time to Japan
  5. Customs and site delivery in Japan 5 days

*It may take more 2-3 days to deliver in Japan for delay of customs clearance or bad weather.

1 -st day Oder
5-th day Start of manufacturing Confirmation, prepare of drawing s – about 5 days)
45-50-th day Finish of manufacturing 30-33 working days (total about 40- 45days)
50-55-th day Prepare for delivery Transfer to port, loading (about 5 days
By Air (about 7-10 days
57-65-th day Arrival to port (Japan) Customs, local delivery (about 5 days)
62-70 days Delivery term Train and Sea (about 25-35 days
75-90-th day Arrival to port (Japan) Customs, local delivery (about 5 days)
80-95 days Delivery term By Sea (about 30-50 days)
82-107-th day Arrival to port (Japan) Customs, local delivery (about 5 days)
87-112 days Delivery term

(Delivery to Hokkaido is likely to take 2-3 days as an additional)